Hi everyone. I am trying to duplicate a project only copying the structures, duration, predecessors and names. Basically, I just want to copy-paste the following columns: 1. Parent ID (Just to transfer the structure to the project, if there is a better way, I am open to hearing it) 2. Name 3. Duration 4. Predecessors I've tried copy-pasting this 4 columns, but predecessors are not transfering correctly, and Parend ID does not change when I paste. Any help is appreciated!
Hello friend, thanks for the reply. No, no constraints, and everything is at 0% completion (also checked if there were any actual start dates and all the fields are empty. Picture attached, also no actual start or finish for the entire project.). Maybe worth mentioning, this project was imported from MS project 2007, this does not happen with files I create directly on PL. What seems strange is that making any changes to the Project information tab will revert the end date to the one set up at the...
Hi everyone. I am having an issue when backwards scheduling. This problem occurs when using backwards scheduling. For some reason, when I am using this mode, and change work, it seems PL decides to ignore the End date you've set up. However, if you go to the project information window, and change anything (for example, the name), it will revert to the original date. I have attached a short video to show what the issue is. Please let me know if you need any extra information, I am new here.